Valencia Road Extension

Houghton Road to Old Spanish Trail


Construction Cost: $14,027,097
Project Status: In Construction
Completion Date: Late 2020
Engineer/Contractor: Psomas/KE&G
Description: KE&G, under contract with Rocking K Development, is constructing 2.6 miles of two-lane roadway between Houghton Road and Old Spanish Trail. The project also includes a new bridge over the Pantano Wash and associated soil cement bank protection, bike lanes and landscaping.
Documents: Sealed Project Plans 2019-03.pdf

Valencia Extension Project Exhibit.pdf

Valencia Extension Resident Letter.pdf

Description: KE&G, under contract with Rocking K Development, is constructing 2.6 miles of two-lane roadway between Houghton Road and Old Spanish Trail. The project also includes a new bridge over the Pantano Wash and associated soil cement bank protection, bike lanes and landscaping.
Contact Information: Andrew McGovern, PE
Resident Engineer, Psomas
Email: valencia@psomas.com
Construction Alerts:
08/31/2020 The Pantano Wash bridge deck was poured in mid-August. The Contractor is now working on traffic barriers so that the road can open in December.
Construction Photos:
08/07/2020 Location 1 - Valencia Road at Mica Mountain High School (View Photos)
Location 2 - Beginning of new Valencia Road alignment (View Photos)
Location 3 - Cutting through large hills on new Valencia Road alignment (View Photos)
Location 4 - Approach to bridge looking eastbound (View Photos)
Location 5 - New Valencia Road/Old Spanish Trail intersection (View Photos)
Location 6 - Valencia Road matching into existing Old Spanish Trail (View Photos)