Valencia Road Extension

Houghton Road to Old Spanish Trail


Construction Cost: $14,027,097
Project Status: In Construction
Completion Date: Late 2020
Engineer/Contractor: Psomas/KE&G
Description: KE&G, under contract with Rocking K Development, is constructing 2.6 miles of two-lane roadway between Houghton Road and Old Spanish Trail. The project also includes a new bridge over the Pantano Wash and associated soil cement bank protection, bike lanes and landscaping.
Documents: Sealed Project Plans 2019-03.pdf

Valencia Extension Project Exhibit.pdf

Valencia Extension Resident Letter.pdf

Description: KE&G, under contract with Rocking K Development, is constructing 2.6 miles of two-lane roadway between Houghton Road and Old Spanish Trail. The project also includes a new bridge over the Pantano Wash and associated soil cement bank protection, bike lanes and landscaping.
Contact Information: Andrew McGovern, PE
Resident Engineer, Psomas
Email: valencia@psomas.com
Construction Alerts: Construction activities are occurring on Valencia Road east of Houghton Road. Please pay attention to construction signage and watch out for workers.
04/28/2020 Construction of the Pantano Wash Bridge is underway. This two-lane bridge will be 370 feet long, with three spans of just over 120 feet each. The current schedule calls for completion of the bridge in September. Photos of the bridge construction will be updated regularly. (View Photos)
Construction Photos:
06/12/2020 Location 1 - Valencia Road at Mica Mountain High School (View Photos)
Location 2 - Beginning of new Valencia Road alignment (View Photos)
Location 3 - Cutting through large hills on new Valencia Road alignment (View Photos)
Location 4 - Approach to bridge looking eastbound (View Photos)
Location 5 - New Valencia Road/Old Spanish Trail intersection (View Photos)
Location 6 - Valencia Road matching into existing Old Spanish Trail (View Photos)